Garnier Road, Winchester, will remain closed until late January.

Heavy rain and an unforeseen need to divert gas and electricity supplies have put bridge replacement work back by a fortnight and the replacement of a gas main near a disused railway arch will take a further three weeks.

"They can't be done together but we will do them one after the other to minimise disruption," said a county council spokesman.